Total reconstruction of the existing stadium to include new synthetic turf and running track.
- 1,550 LF – Compost Filter Sock
- 5,554 SY – Remove Track Surface
- 5,554 SY – Mill Track Surface
- 2,317 CY – Topsoil Removal
- 1,723 CY – Bulk Excavation
- 890 CY – Excavation for Underground SWM System
- 890 CY – OGA Backfill (AASHTO #57)
- 1,591 LF – 8” X 12” Cement Concrete Turf Curb
- 1 Pair – Football Goal Post
- 937 LF – Storm Pipe
- 670 LF – 4” Perforated Field Drain
- 626 LF – 8” Perforated Field Drain
- 10,507 SY – 4 OZ Geotextile
- 2,346 CY – 2 Layer Synthetic Turf Drainage Base
- 94,566 SF – Laser Grade Finish Stone
- 523 SY – D Area Asphalt Pavement
- 5,165 SY – 3.5” Binder, 1.5” Wearing Course
- 12,700 SF – Seed & Mulch Disturbed Areas