York City School District

York City School District Turf Field  This project consisted of a completely new synthetic turf system with underground drainage to provide for multiple sporting events at one time. 500′ – Compost Filter Sock8,200 CY – Excess Subsoil2,200′ – Storm Drainage Pipe9 EA – Storm Manholes8 EA – Storm Inlets2,250′ – 12×12 Concrete Curb3,763 CY – #57 […]

Rutter’s – Berkley Springs

Rutter’s Berkeley Springs, WV  Berkeley Springs Rutter’s convenience store located just South of the Pennsylvania Border was completed in the early months of 2025. 2,035′ – Compost Filter Sock5,485 CY – Stripping47,408CY – Excavated Cut2 EA – Terre Hill Storm Water Systems2,700′ – Storm Drainage Pipe15 EA – Storm Inlets 4 EA – Storm Manholes535′ – DR11 Waterline566′ […]

Mifflin County High School

Mifflin County High School This project was made up of four separate fields, which included a multipurpose field, baseball, softball, and a state of the art football stadium. Football Stadium950′ – Compost Filter Sock7,050 CY – Excess Subsoil1,680 CY – #57 Synthetic Turf Drainage360′ – Ball Barrier System620′ – Sanitary Sewer375′ – Waterline Multipurpose Track1385′ – Compost […]

Johnstown Central Park

City of Johnstown Central Park ImprovementsJohnstown, PA  This project includes the removal and replacement of Johnstown’s Central Park. This project includes the following upgrades below. 540′ Compost Filter Sock 1500′ – Perimeter Protection Fence 940′ – Tree Protection Fence980′ – Strom Drainage Piping6 EA – Storm Inlets1 LS – Irrigation System 1 LS – Monument Relocation & Cleaning1 EA […]

Luray Avenue Park

Luray Avenue – Park Play Escape ProjectJohnstown, PA  This project included the installation of brand new basketball, roller hockey, tennis, and pickleball courts. These courts were overlaid with a special coating system to enhance the durability of the surface. These courts were encompassed by asphalt walking paths that connect the other fields to these areas. 3290 […]

Bedford Area High School

Bedford Area School District High SchoolBedford, PA  The Bedford Area School District is receiving renovations to their high school, which includes the new installation of all utilities, dirt work, and brand-new football field. 2,300′ – Compost Filter Sock14,725 CY – Bulk Cut610′ – Gas Line Excavation & Backfill460′ – Sanitary Sewer550′ – Waterline 6,100′ – Storm Drainage […]

Seven Springs Borough

Seven Springs Borough – Stormwater ImprovementsChampion, PA  This project consisted of stormwater renovations along with a new water line to feed the snow making machines. 2,800′ – 15″ Storm Drainage Pipe29 EA – Type M Inlet2 EA – Storm Manholes230′ – 8″ Ductile Waterline900 SY – Temporary Asphalt Restoration  Seven Springs

North Star Elementary

The North Star Elementary School is receiving renovations to construct a new gymnasium which includes the installation of all utilities and dirt work. 1,595′ – Compost Filter Sock3,115 CY – Strip Topsoil8,772 CY – Excavation to Fill575′ – Gasline Excavation & Backfill683′ – Sanitary Sewer 6 EA – Sanitary Sewer Manhole420′ – Waterline 2,489′ – Storm Drainage Pipe9 […]

Westmont Price Field

Total reconstruction of the Westmont Hilltop School District Price Field, the alma mater of the founder of Straw Construction Co., Inc.